Kambar-Ata-1 HPP
Kambar-Ata-1 HPP is a Kyrgyz government-led, trilateral infrastructure project to build a 1,860 MW hydroelectric power plant on the Naryn River, serving domestic Kyrgyz demand and exporting electricity to Kazakhstan and Uzbekistan via the Central Asian Power System.
- Company typePrivate
- Founded1986
- HeadquartersBishkek, Kyrgyzstan
- Headcount501–1,000
- GTM typeB2B
- OfferingServices
What Kambar-Ata-1 HPP does
Kambar-Ata-1 HPP is a government-led hydroelectric infrastructure project being developed by the Ministry of Energy of the Kyrgyz Republic under a trilateral framework with the Republic of Kazakhstan and the Republic of Uzbekistan. The core asset is a planned 1,860 MW hydropower plant on the Naryn River in the Tien-Shan Mountain range, featuring a 261-meter-high concrete dam and a reservoir of 68 km length and 61.2 km² area. The site has a development history dating to 1986 under the Soviet Union; construction was halted in 1991 and the project was relaunched as a national priority in June 2022 by President Sadyr Japarov.
The project is currently in the preparation phase, with a 2014 feasibility study being updated by Swiss engineering firm AFRY and an Environmental and Social Impact Assessment being conducted by SMEC International since July 2024, both supported by a World Bank-led Donor Coordination Committee that includes ADB, AIIB, the EU, EIB, EBRD, IsDB, the OPEC Fund, the Arab Coordination Group, Italy's CDP, UK FCDO, and Switzerland. The output — when operational — will be electricity distributed into the Kyrgyz national grid and exported via the Central Asian Power System (CAPS) to Kazakhstan and Uzbekistan, targeting a regional market of approximately 80 million people with energy demand expected to grow roughly 40% by 2030. As a state infrastructure initiative rather than a commercial enterprise, Kambar-Ata-1 HPP has no commercial pricing model, no revenue to date, and no private equity ownership structure; financing is multilateral and concessional, coordinated by the World Bank.
Kambar-Ata-1 HPP firmographics
Firmographics- Name
- Kambar-Ata-1 HPP
- Legal name
- Ministry of Energy of the Kyrgyz Republic (Камбаратинская ГЭС-1)
- Website
- https://kambarata1.org
- Company type
- Private
- Founded year
- 1986
- Operating status
- Operating
- Headcount range
- 501–1,000 employees
- Short description
- Kambar-Ata-1 HPP is a Kyrgyz government-led, trilateral infrastructure project to build a 1,860 MW hydroelectric power plant on the Naryn River, serving domestic Kyrgyz demand and exporting electricity to Kazakhstan and Uzbekistan via the Central Asian Power System.
- Ownership category
- akta.pro rank
Kambar-Ata-1 HPP industry classification
Industry- Product category
- Hydropower Generation
- NAICS
- Hydroelectric Power Generation (221111), Utility System Construction (2371), Electric Power Generation, Transmission and Distribution (2211)
- SIC
- Electric Services (4911), Water, Sewer, Pipeline, Comm & Power Line Construction (1623)
- akta.pro primary industry
- Reservoir/Impoundment Hydroelectric Generation (EUACAEAB)
- akta.pro secondary industries
- Hydropower Plant EPC (Dam, Run-of-River, Pumped Hydro Civil Works) (EUAEAAAD), Hydro BOP Civil & Water Conveyance (Dams, Spillways, Penstocks, Canals) (EUAMAFAG), Power Generation Plant Construction (Thermal, Hydro, Nuclear) (IMAFADAC)
Keywords
Where Kambar-Ata-1 HPP is headquartered
LocationHeadquarters
- HQ city
- Bishkek
- HQ country
- Kyrgyzstan
- HQ region
- Asia
Offices3 records
Markets served
Kambar-Ata-1 HPP business model
Business model- GTM type
- B2B
- Offering type
- Services
- Cost components
- Infrastructure, Technology or R&D, Operations, Personnel, Supply Chain
Revenue model
- Electricity Generation and Sales: The project will generate 1860 MW of clean hydroelectric power for domestic consumption in Kyrgyzstan and export to neighboring Kazakhstan and Uzbekistan, contributing to regional energy security and decarbonization goals.
Go-to-market motion1 record
Distribution channels2 records
Marketing channels5 records
Kambar-Ata-1 HPP product offering
Product offeringCore offering
Kambar-Ata-1 HPP is a planned 1,860 MW hydroelectric power plant to be built on the Naryn River in the Kyrgyz Republic, featuring a 261-meter concrete dam and a 68 km reservoir. Once operational, the facility will generate renewable electricity for domestic consumption in Kyrgyzstan and export to Kazakhstan and Uzbekistan via the Central Asian Power System (CAPS). The project is in pre-construction phase, supported by feasibility studies, ESIA documentation, and World Bank-led technical assistance.
Product overview
Kambarata-1 HPP is a transformational regional clean energy infrastructure project led by the Ministry of Energy of the Kyrgyz Republic, aimed at enhancing energy security and strengthening regional cooperation in Central Asia. The core offering is the 1860 MW hydropower plant with its 261-meter concrete dam. The project portfolio includes supporting components: the Feasibility Study (developed by Swiss company AFRY) and Environmental and Social Impact Assessment (prepared by international firm SMEC), both funded through World Bank Technical Assistance. The Grievance Redress Mechanism provides stakeholder complaint resolution. As a national infrastructure initiative rather than a software product, the project does not include API products, software integrations, or AI capabilities.
Differentiator
Problem solved
Functional benefit
Products and services
- Kambarata-1 Hydropower Plant (HPP) A 1,860 MW hydroelectric power plant on the Naryn River featuring a 261-meter-high concrete dam creating a 68 km long reservoir with 61.2 km² area, intended to generate renewable electricity for domestic consumption in Kyrgyzstan and export to Kazakhstan and Uzbekistan.
Quantifiable outcome
- 1,860 MW capacity serving ~80 million people across Central Asia
- +2 more outcomes
Companies that use Kambar-Ata-1 HPP
Customer profileSegments3 records
Ideal customer profiles3 records
Kambar-Ata-1 HPP technology and API
TechnologyTechnology focussed No
API detail
- Has API
- No
- API docs
- API detail
Core technology
AI maturity
App detail
Feature1 record
Kambar-Ata-1 HPP partnerships and signals
Strategic signalPartnerships
Four partnerships are on record, tiered core/flagship.
- AFRY (Swiss Engineering Company)core/flagshipAFRY, a Swiss engineering consulting firm, was selected through competitive process in 2024 to update the feasibility study, including seismic analysis, hydrological assessments, and key engineering solutions.
- SMEC Internationalcore/flagshipSMEC, an international environmental and social consulting firm, has been conducting Environmental and Social Impact Assessment (ESIA) since July 2024 in line with Kyrgyz regulations and international best practices, including World Bank ESS10 requirements.
- Republic of Kazakhstancore/flagshipKazakhstan is a joint development partner in the Kambarata-1 HPP. The intergovernmental agreement signed in June 2024 commits both countries to joint project implementation. Kazakhstan provides political commitment and participates in financing through the Donor Coordination Committee.
- Republic of Uzbekistancore/flagshipUzbekistan is a joint development partner. The trilateral agreement commits Uzbekistan to the joint development, with the country providing political support and participating in regional energy cooperation frameworks including CAPS.
Scale indicators6 records
Expansion highlights5 records
Kambar-Ata-1 HPP competitors and assessment
Company assessmentMarket position
Competitive moat3 records
Key risks6 records
Key highlights7 records
Customer concentration
Kambar-Ata-1 HPP social profiles
Digital presenceKambar-Ata-1 HPP financial estimates
Financial estimateRevenue estimate
Valuation estimate
Kambar-Ata-1 HPP leadership team
Management profileNumber of profiles
Kambar-Ata-1 HPP funding detail
Funding detailFunding overview
Funding rounds
Investors
Funding detail is available on the Subscription and Enterprise plan.Contact sales →
Kambar-Ata-1 HPP M&A and investment
M&A and investmentM&A
Investments
M&A and investment is available on the Subscription and Enterprise plan.Contact sales →
Frequently asked questions about Kambar-Ata-1 HPP
What does Kambar-Ata-1 HPP do?
Kambar-Ata-1 HPP is a planned 1,860 MW hydroelectric power plant to be built on the Naryn River in the Kyrgyz Republic, featuring a 261-meter concrete dam and a 68 km reservoir. Once operational, the facility will generate renewable electricity for domestic consumption in Kyrgyzstan and export to Kazakhstan and Uzbekistan via the Central Asian Power System (CAPS). The project is in pre-construction phase, supported by feasibility studies, ESIA documentation, and World Bank-led technical assistance.
Is Kambar-Ata-1 HPP a public or private company?
Kambar-Ata-1 HPP is a private company. It is classified as state government owned and is currently operating.
When was Kambar-Ata-1 HPP founded?
Kambar-Ata-1 HPP was founded in 1986. It employs 501 to 1,000 people.
Where is Kambar-Ata-1 HPP based?
Kambar-Ata-1 HPP is headquartered in Bishkek, Kyrgyzstan, in the Asia region.
How does Kambar-Ata-1 HPP make money?
One revenue line is on record: electricity Generation and Sales.
Does Kambar-Ata-1 HPP have an API?
No public API is recorded for Kambar-Ata-1 HPP.
What industry is Kambar-Ata-1 HPP in?
Kambar-Ata-1 HPP's product category is Hydropower Generation. Its primary akta.pro industry code is EUACAEAB, Reservoir/Impoundment Hydroelectric Generation, with a secondary code of EUAEAAAD, Hydropower Plant EPC (Dam, Run-of-River, Pumped Hydro Civil Works). Its NAICS code is 221111 and its SIC code is 4911.