Elektrárna Dukovany II
Elektrárna Dukovany II is a Czech sovereign-controlled special-purpose vehicle building two KHNP APR1000 Gen III+ reactors at the Dukovany site, which will supply approximately 11-12% of Czech electricity upon completion in the late 2030s.
- Company typePrivate
- Founded2015
- HeadquartersPrague, Czechia
- Headcount101–250
- GTM typeB2B
- OfferingServices
What Elektrárna Dukovany II does
Elektrárna Dukovany II (EDU II) is a Czech special-purpose vehicle established in 2015 to construct two new nuclear reactor units at the existing Dukovany nuclear power plant site, utilizing Korea Hydro & Nuclear Power's APR1000 Gen III+ pressurized water reactor technology. The project represents the largest single investment in the history of the Czech Republic and, once operational, is projected to generate approximately 11-12% of the country's total electricity consumption. Originally founded by ČEZ, the dominant Czech utility, majority ownership was transferred to the Czech state via the Ministry of Finance in May 2025, with ČEZ retaining approximately 20% as a strategic minority shareholder. The company is headquartered in Prague.
EDU II is currently in its preparation phase, with construction scheduled to commence in 2029 and trial operation targeted for 2036-2037. The project pursues a 60% Czech supplier localization target and has entered fuel and training arrangements with KEPCO Nuclear Fuel commencing in 2026. Conceptual design was completed in April 2026. Revenue generation will not commence until commercial operation begins, with electricity sales directed to the Czech national grid under a regulated framework. Euratom endorsement and the sovereign-backed ownership structure position the project as national critical infrastructure rather than a competitive commercial venture.
Elektrárna Dukovany II firmographics
Firmographics- Name
- Elektrárna Dukovany II
- Legal name
- Elektrárna Dukovany II, a. s.
- Website
- https://njzedu.cz
- Company type
- Private
- Founded year
- 2015
- Operating status
- Operating
- Headcount range
- 101–250 employees
- Short description
- Elektrárna Dukovany II is a Czech sovereign-controlled special-purpose vehicle building two KHNP APR1000 Gen III+ reactors at the Dukovany site, which will supply approximately 11-12% of Czech electricity upon completion in the late 2030s.
- Ownership category
- akta.pro rank
Elektrárna Dukovany II industry classification
Industry- Product category
- Nuclear Power Generation
- NAICS
- Nuclear Electric Power Generation (221113)
- SIC
- Electric Services (4911)
- akta.pro primary industry
- Nuclear Plant EPC & Construction (EUAEAAAC)
- akta.pro secondary industry
- Power Generation Plant Construction (Thermal, Hydro, Nuclear) (IMAFADAC)
Keywords
Where Elektrárna Dukovany II is headquartered
LocationHeadquarters
- HQ city
- Prague
- HQ country
- Czechia
- HQ region
- Europe
Offices1 record
Markets served
Elektrárna Dukovany II business model
Business model- GTM type
- B2B
- Offering type
- Services
- Cost components
- Infrastructure, Supply Chain, Personnel, Operations, Technology or R&D
Revenue model
- Electricity Generation and Sales: Elektrárna Dukovany II operates as a nuclear power plant investor that will generate and sell electricity to the Czech national grid. Once operational (planned 2036-2037), the plant will produce approximately 11-12% of Czech Republic's electricity consumption, supplying 3.2-3.5 million households. Revenue is generated through long-term power purchase agreements and electricity market sales.
Go-to-market motion1 record
Distribution channels1 record
Marketing channels5 records
Elektrárna Dukovany II product offering
Product offeringCore offering
Elektrárna Dukovany II is the investor and project company responsible for building two new nuclear power reactor units (APR1000 Generation III+ technology) at the Dukovany site in the Czech Republic. The project is the largest single investment in Czech history, with construction scheduled to begin in 2029 and trial operation planned for 2036–2037. Once operational, the two units will have a combined installed capacity of approximately 1,520–1,627 MWe and are expected to supply around 11–12% of the Czech Republic's total electricity consumption.
Product overview
Elektrárna Dukovany II is a special-purpose vehicle (a.s.) established to invest in and manage the construction of new nuclear power units at the Dukovany site. The company is building two APR1000 reactor units (Units 5 and 6) in partnership with South Korean contractor KHNP under a turnkey EPC contract. The project involves the complete engineering, procurement, construction, and commissioning of the nuclear facility, including nuclear fuel supply. The new units will have a combined installed capacity of approximately 1,520-1,627 MWe and are expected to operate for 60+ years, supplying approximately 11-12% of Czech Republic's electricity consumption.
Differentiator
Problem solved
Functional benefit
Products and services
- New Nuclear Units at Dukovany (Nový jaderný zdroj Dukovany) Two new nuclear power reactor units (Units 5 and 6) being built at the Dukovany site in the Czech Republic using KHNP's APR1000 Generation III+ pressurised water reactor technology under a turnkey EPC contract. Once operational, the units will deliver approximately 1,520–1,627 MWe of baseload low-carbon electricity to the Czech national grid, supplying around 11–12% of national electricity consumption and powering roughly 3.2–3.5 million households over a 60+ year service life at 90% availability.
Quantifiable outcome
- Supplies 11-12% of Czech Republic electricity consumption
- +5 more outcomes
Companies that use Elektrárna Dukovany II
Customer profileNamed customers1 record
Segments1 record
Ideal customer profiles1 record
Elektrárna Dukovany II technology and API
TechnologyTechnology focussed No
API detail
- Has API
- No
- API docs
- API detail
Core technology
AI maturity
App detail
Feature4 records
Elektrárna Dukovany II partnerships and signals
Strategic signalPartnerships
Four partnerships are on record, tiered core and minor.
- KHNP (Korea Hydro and Nuclear Power)coreSouth Korean company KHNP is the main contractor for the two new nuclear units at Dukovany. Selected in a highly competitive international tender for its APR1000 project. Contract signed June 2025 covering entire turnkey EPC (Engineering, Procurement, and Construction) delivery including fuel supply. Under government agreement, KHNP aims to involve Czech companies for more than half of all deliveries.
- ČEZ Energetické produktyminorCzech company that conducted the geological surveys for the new units. Completed the survey including 6,000+ page final report with geological, geophysical, geodetic, and geotechnical interpretation. Contract worth several hundred million CZK.
- Doosan Škoda PowerminorCzech company based in Plzeň that won a contract for the supply and manufacture of turbogenerators for the new nuclear units.
- Energoprojekt PrahaminorCzech engineering company providing expert consulting services for licensing and safety analyses. Also participating in project documentation preparation and reviewing conceptual design from KHNP.
Scale indicators10 records
Recent moves7 records
Expansion highlights5 records
Elektrárna Dukovany II competitors and assessment
Company assessmentOthers
- Westinghouse Electric Company: U.S. nuclear technology provider offering AP1000 reactor design, the principal Western alternative to APR1000. Comparable as a key nuclear technology/EPC ecosystem player, not a direct operator peer.
- Energoatom: Ukrainian state operator of 15 RBMK and VVER reactors, and active developer of new VVER-1000 capacity. Comparable as an Eastern European state nuclear operator with new-build ambitions in a conflict-affected region.
- KHNP (Korea Hydro & Nuclear Power): South Korean state-owned nuclear EPC and operator and the primary contractor for EDU II. Comparable as the APR1000 platform provider and likely counterparty for adjacent Central European new-builds.
Direct peers
- Teollisuuden Voima Oy (TVO): Finnish nuclear operator running Olkiluoto 1-3, including the recently commissioned Olkiluoto 3 EPR. Direct comparable for European first-of-a-kind nuclear new-build execution risk and merchant baseload economics.
- Slovenské elektrárne: Slovak nuclear operator running Bohunice and Mochovce NPPs, with a major new-build (Mochovce 3&4) under construction. Regional peer with similar PWR/Russian technology base and Central European grid context.
- ČEZ, a.s. Czech state-controlled utility that operates the existing Dukovany Units 1-4 and Temelín nuclear plants and retains a ~20% stake in EDU II. The most direct comparable given identical Czech geography, nuclear operations, and partial ownership overlap.
- MVM Paks II: Hungarian state-owned special-purpose vehicle building two new VVER-1200 nuclear units at Paks, financed largely by Russia. Closest analog by structure: state-backed, EU-member nuclear new-build SPV targeting domestic baseload supply.
Emerging players
- PGE EJ1: Polish state-backed SPV responsible for Poland's first nuclear power plant (Choczewo, 3 GWe AP1000). Comparable as a Central European state-led nuclear SPV in the early project development phase, though earlier-stage than EDU II.
Broad incumbents
- EDF / EDF Energy (NNB): France's state-controlled nuclear major and operator of Hinkley Point C (UK) and Flamanville 3. Direct parallel as a state-backed European utility executing large new-build programs under similar regulatory regimes.
- CGN (China General Nuclear Power Group): One of the world's largest nuclear operators with a portfolio of 27+ reactors, supplying domestic Chinese baseload. Comparable as a state-aligned nuclear major with multi-decade build programs and proprietary reactor designs.
Market position
Strengths5 records
Weaknesses5 records
Competitive moat4 records
Key risks6 records
Key highlights7 records
Customer concentration
Elektrárna Dukovany II social profiles
Digital presenceElektrárna Dukovany II financial estimates
Financial estimateRevenue estimate
Valuation estimate
Elektrárna Dukovany II leadership team
Management profileNumber of profiles
Profiles2 records
Elektrárna Dukovany II funding detail
Funding detailFunding overview
Funding rounds
Investors
Funding detail is available on the Subscription and Enterprise plan.Contact sales →
Elektrárna Dukovany II M&A and investment
M&A and investmentM&A
Investments
M&A and investment is available on the Subscription and Enterprise plan.Contact sales →
Frequently asked questions about Elektrárna Dukovany II
What does Elektrárna Dukovany II do?
Elektrárna Dukovany II is the investor and project company responsible for building two new nuclear power reactor units (APR1000 Generation III+ technology) at the Dukovany site in the Czech Republic. The project is the largest single investment in Czech history, with construction scheduled to begin in 2029 and trial operation planned for 2036–2037. Once operational, the two units will have a combined installed capacity of approximately 1,520–1,627 MWe and are expected to supply around 11–12% of the Czech Republic's total electricity consumption.
Is Elektrárna Dukovany II a public or private company?
Elektrárna Dukovany II is a private company. It is classified as state government owned and is currently operating.
When was Elektrárna Dukovany II founded?
Elektrárna Dukovany II was founded in 2015. It employs 101 to 250 people.
Where is Elektrárna Dukovany II based?
Elektrárna Dukovany II is headquartered in Prague, Czechia, in the Europe region.
How does Elektrárna Dukovany II make money?
One revenue line is on record: electricity Generation and Sales.
Who are Elektrárna Dukovany II's main competitors?
Others on record are Westinghouse Electric Company, Energoatom and KHNP (Korea Hydro & Nuclear Power). Direct peers are Teollisuuden Voima Oy (TVO), Slovenské elektrárne, ČEZ, a.s. and MVM Paks II. PGE EJ1 is listed as an emerging player. Broad incumbents are EDF / EDF Energy (NNB) and CGN (China General Nuclear Power Group).
Does Elektrárna Dukovany II have an API?
No public API is recorded for Elektrárna Dukovany II.
What industry is Elektrárna Dukovany II in?
Elektrárna Dukovany II's product category is Nuclear Power Generation. Its primary akta.pro industry code is EUAEAAAC, Nuclear Plant EPC & Construction, with a secondary code of IMAFADAC, Power Generation Plant Construction (Thermal, Hydro, Nuclear). Its NAICS code is 221113 and its SIC code is 4911.